Day 3, Wednesday. With the rafters in place, the posts for the east wall are now dug in.
The ruts got deeper and the rain that night filled them again.
Day 4, Thursday. All the main posts are in position and most of the wall girts are fastened on. Also, the purlins are on the roof, extending beyond the building to allow for the overhang that is to come.
The water-filled ruts became deeper and that night, even more rain fell, filling them once again. To allow for the site to dry out, no further work was done until the following Monday.